PROJECT 04 · SEATAC, WA
HOA meter upgrades.
Reliable power.
Five Challenger six-pack meter assemblies replaced with new Eaton equipment.
Back to all projectsTHE PROJECT
New meters. Coordinated from start to finish.
For this SeaTac HOA, Shudko Electric replaced five aging Challenger six-pack meter assemblies with new Eaton meter packs. The old equipment had rust, cracked seals and water intrusion that was causing breakers to trip. We obtained all required permits and passed all required inspections and approvals from Puget Sound Energy and the City of SeaTac. We coordinated utility disconnection and reconnection and completed one meter pack per day to minimize power interruptions for apartment residents. The completed installation provides safer, more reliable electrical service for the community.
- Replaced five aging Challenger six-pack meter assemblies with Eaton meter packs
- Addressed rust, cracked seals and water intrusion
- Obtained all required permits
- Passed all required PSE and City of SeaTac inspections and approvals
- Coordinated utility disconnection and reconnection
- Completed one meter pack per day to minimize resident outages